Keep the measured work item distinct from the material purchase.
Connect BOQ descriptions, units, allowances and commercial purchases without hiding the conversion.
Start with the work description
A BOQ line describes a measured item within a stated scope. Before using its quantity for procurement, read the description, drawing reference, unit and inclusions. The quantity of finished work is not automatically the quantity of every material used to produce it.
Show the path from work to purchase
Record the relevant dimensions and deductions, then identify the material specification and commercial unit. Keep any allowance and whole-pack rounding separate. This makes it possible to explain why the order proposal differs from the net measured quantity.
Use the slab example carefully
The demo measures a uniform 10 × 8 × 0.15 m slab: 12 m³. A chosen 5% allowance produces 12.6 m³. At illustrative ZAR1,100 per m³, the concrete-material subtotal is ZAR13,860.
It is not a complete concrete work price. Preparation, reinforcement, formwork, labour, pumping, testing, equipment, delivery and tax are separate. Thickness, specification and allowance are demonstration inputs, not a design recommendation or supplier ordering rule.
Explain a revision at the right level
A larger measured element, a new allowance, a product change and a revised rate can all alter the total. Show which decision changed rather than replacing the original figure without explanation. Keep the source drawing revision beside the calculation.
- Read the BOQ item and its unit.
- Identify the material conversion basis.
- Show net quantity and allowance separately.
- Confirm product and purchase unit.
- Record exclusions and unresolved information.
TB supports quantity, purchasing, cost and resource planning. It does not interpret contractual obligations, determine entitlement or certify design. Review the actual work description and construction details with the responsible professionals before purchasing.